Contractor
The City has hired the firm Linaweaver Construction, Inc. for the project. The work includes concrete patchwork as needed, milling off the old asphalt, making base repairs as needed and repaving the roadway with new asphalt.
Traffic Impacts
Local traffic will be allowed in the work zone on milling days; however, on paving days, no traffic will be allowed on the roadway. You will receive notification from the contractor prior to paving days so that you can move your vehicles out of the work zone.
Thank you in advance for your cooperation and patience during this project. If you have any questions please feel free to contact me at 913-362-9620 or jlee@missionhillsks.gov or Marcus Linaweaver, Linaweaver Construction, Inc. at 913-683-1809 or marcus@linaweaver.com. We will make every effort to answer your questions or accommodate your situation.
Street | Tentative Mill/Pave Dates |
Shadow Lane | Oct. 15-16 |
East Mission Drive (Shadow Lane to 56th Street) | Oct. 15-16 |
63rd Street (Wenonga to Belinder) | Oct. 21-22 |
Brookbank Lane | Oct. 23-24 |
Belinder (Mission Drive to Belinder Low Water Crossing) | Oct. 23-24 |
Pembroke Lane | Oct. 27-28 |
55th Street | Oct. 27-28 |
High Drive (67th Street to 68th Street) | Oct. 29-30 |
Guilford Lane | Nov. 6-7 |
Brookwood | Nov. 17-19 |
59th Street | Nov. 24-26 |
Pembroke Court | Nov. 24-26 |