The City's street crack sealing program will begin Tuesday, July 23rd and continue to through the first week of August. There will be a rolling closure at the locations of the street crack sealing. The sequetial order for crack sealing is as follows:
1. W. 67th Terrace: State Line to High Drive
2. Rainbow: Willow to 68th Street
3. Overhill Circle (cul de sac accessed between 5930 and 5944 Overhill)
4. Broobank Lane
5. Belinder: Tomahawk to 70th Terrace
6. Aberdeen: 63rd Street to Tomahawk
7. 70th Street cul de sac
8. 67th Street: Belinder to 67th Terrace
9. 66th Terrace: Belinder to Tomahawk
10. 6400 Block of Overbrook
11. 6400 Block of High Drive